More than four years after construction began in Poush 2079, the much-awaited six-lane expansion of the Suryabinayak–Dhulikhel road along the Araniko Highway remains incomplete, leaving commuters to travel over a road that is smooth and blacktopped in some stretches but dusty and muddy in others. The project, which was launched with the promise of easing traffic along one of the busiest corridors connecting Bhaktapur with Kavrepalanchok, has failed to meet its expected pace, and the sight of half-finished road sections has become a familiar frustration for daily travellers.
The expansion work has been divided into two sections to make implementation more manageable. The first section stretches 7.5 kilometres from Suryabinayak to Sanga, with an estimated investment of about Rs 3.88 billion, while the second section covers 8.4 kilometres from Sanga to Dhulikhel at an estimated cost of about Rs 4.564 billion. Together, the two sections are intended to transform the entire Suryabinayak–Dhulikhel stretch into a modern six-lane highway, but four years on, that vision is yet to materialise on the ground.
A Road of Two Realities
Perhaps the most striking aspect of the project today is the uneven state of the corridor. On some stretches, drivers enjoy a paved, smooth surface that reflects the kind of infrastructure the project promised. But just a few kilometres away, the picture changes dramatically. Other sections remain unpaved, covered in dust during dry weather and turning into muddy tracks when it rains. This patchwork of conditions means commuters never know what kind of road they will encounter along the way.
For the thousands of people who travel this route daily between Bhaktapur, Banepa and Dhulikhel, the incomplete state of the road has translated into longer and less predictable journeys. Dust raised by passing vehicles on unfinished sections affects not only drivers and passengers but also residents, shopkeepers and students living along the corridor, who have been waiting for the completion of the expansion to bring relief from years of disruption.
Progress Below Expectations
According to reports on the project's status, progress over the four years of construction has simply not met expectations. A project of this scale, split into two contract packages worth a combined sum exceeding Rs 8.4 billion, was expected to show more visible advancement by now. Instead, the corridor remains a work in progress, with significant portions still awaiting completion.
The gap between the two sections is also notable in terms of scale and investment. The Sanga–Dhulikhel section, at 8.4 kilometres and about Rs 4.564 billion, is both longer and more expensive than the Suryabinayak–Sanga section, which covers 7.5 kilometres at about Rs 3.88 billion. How each of these sections has progressed independently helps explain the mixed picture now visible along the highway, where the quality and completeness of the road can change abruptly from one stretch to the next.
What the Incomplete Road Means for Commuters
The Araniko Highway corridor through Suryabinayak, Sanga and Dhulikhel is a vital link, serving local traffic within the Kathmandu Valley's eastern edge as well as travellers heading toward the hills of Kavrepalanchok. The six-lane expansion was conceived to accommodate growing vehicle numbers and to reduce the congestion that has long plagued this route. Until the work is finished, however, commuters continue to bear the costs of the delay in the form of slow movement, dust and mud.
The contrast along the route has been documented in detail by local media. RatoPati's report on the project described the situation as one where the road is "somewhere smooth, somewhere still dusty," capturing in a phrase the daily experience of those who use the highway. Similar coverage from Khabarhub and Arthasarokar has highlighted how, four years after work began in Poush 2079, the promise of a fully expanded six-lane road remains out of reach.
A Waiting Game for the Corridor
With the construction period now well past the four-year mark, the question hanging over the Suryabinayak–Dhulikhel expansion is when, and how quickly, the remaining work can be brought to completion. The project's combined budget of roughly Rs 8.44 billion across its two sections represents a significant public investment, and the incomplete state of the road means that investment has yet to deliver its full benefit to the public.
For now, the corridor tells a story of ambition only partially realised. Paved sections hint at what the finished highway will offer, while the dusty and muddy stretches serve as a daily reminder of work still pending. As commuters continue to navigate the uneven road, the completion of the Suryabinayak–Sanga and Sanga–Dhulikhel sections remains one of the most closely watched infrastructure projects in the region, with residents and road users alike hoping the remaining stretches will finally be finished.
- The six-lane expansion began in Poush 2079 and remains incomplete after more than four years.
- The project covers two sections: Suryabinayak–Sanga (7.5 km, about Rs 3.88 billion) and Sanga–Dhulikhel (8.4 km, about Rs 4.564 billion).
- Some stretches of the road are paved and smooth, while others remain dusty and muddy.
- Progress has not met expectations, according to media reports documenting the project's status.
Further details on the project's progress are available in the original reporting by RatoPati, Khabarhub and Arthasarokar.