The lack of a diversion structure at Hemba Khola along the under-construction Tamor Corridor road in Panchthar district has left local transport severely disrupted, with no attempt made to build a crossing even as winter sets in and the water level in the stream recedes. According to reports, two-wheelers, three-wheelers and small four-wheelers cannot operate on this section of the road without a diversion, and transport there has been affected for the past eight months.
With the stream's water flow now decreasing, the Phidim–Mulghat section has come into regular operation. However, on the Phidim–Kabeli section, only large vehicles are currently able to make the crossing, leaving smaller vehicles and the passengers who depend on them without reliable service.
Winter Passes Without a Diversion
The construction of a diversion at Hemba Khola is typically feasible during the winter months, when the water level in streams and rivers drops and work can be carried out in the riverbed. Despite these favourable conditions arriving, reports indicate that no attempt has been made to build the diversion at the site.
The delay has prolonged the hardship for communities along the corridor. For eight months, transport on this section has been affected, forcing commuters to rely on large vehicles alone or abandon travel altogether. Two-wheelers, three-wheelers and small four-wheelers, which form the backbone of local transport in the hill districts, remain unable to use the route.
Uneven Service on the Corridor
The situation along the corridor is currently uneven. The Phidim–Mulghat section has returned to regular operation as the flow of water in the stream has decreased, allowing vehicles to pass. By contrast, the Phidim–Kabeli section remains accessible only to large vehicles.
This restriction means that daily commuters, students, patients and traders who depend on smaller vehicles face continued difficulty in movement. Local transport operators of small vehicles have been unable to resume services on the affected section, keeping the route's connectivity incomplete despite the seasonal drop in water levels.
Tamor Corridor's Ongoing Construction
The Tamor Corridor road is still under construction, and the Hemba Khola crossing is one of the points where the unfinished state of the project is directly felt by the public. Until a diversion is built at the stream, the section will remain impassable for smaller vehicles regardless of the season's favourable conditions.
The reports highlight that the failure to take advantage of the winter season to construct the diversion risks extending the disruption further. As long as the Hemba Khola crossing remains without a diversion, transport along the Phidim–Kabeli section is expected to stay restricted to large vehicles, and the full benefits of the corridor for local residents will remain out of reach.