The Muglin–Malekhu road expansion, the third package of the Prithvi Highway's Nagdhunga–Muglin road upgrading project, remains less than half complete a full year after its contract deadline expired. The stretch, which falls in Chitwan, has seen physical progress of only 46 percent even after two deadline extensions, leaving commuters along one of the country's busiest highway corridors to endure continued delays and disruption.
Contract timeline and current status
The contract for the Muglin–Malekhu section was awarded on Poush 15, 2079 BS, with an original completion deadline set for Poush 15 last year. As of now, work on the stretch is still incomplete, with payment progress standing at just 46 percent, according to reports from Chitwan.
The deadline has already been extended twice, yet the pace of construction has failed to pick up meaningfully. A full year after the contracted completion date passed, the project remains far from the finish line, raising questions about the contractor's capacity and the oversight of the project by the concerned authorities.
Impact on commuters and the highway corridor
The Nagdhunga–Muglin road section is a vital link connecting Kathmandu with the rest of the country, and the Muglin–Malekhu stretch is a key component of its upgrade. Prolonged construction on this section has made travel along the Prithvi Highway slower and more difficult, affecting passenger buses, freight vehicles and daily commuters alike.
Delays in highway expansion projects of this kind typically translate into ongoing dust, narrow carriageways and traffic bottlenecks for road users. With the Muglin–Malekhu package still only 46 percent complete, travellers between Kathmandu, Chitwan and destinations further west continue to face the inconveniences of an unfinished road.
Questions of accountability
The fact that the expansion lags a year past its deadline despite two extensions points to weaknesses in contract management and monitoring. Awarded with a completion schedule that has long since lapsed, the project's slow progress has become a point of concern for those tracking infrastructure delivery along the Prithvi Highway.
As reported from Chitwan, the slow pace of work on the Muglin–Malekhu stretch underscores a familiar pattern in Nepali road expansion projects, where repeated deadline extensions have become common. Unless the pace of construction accelerates sharply, the upgraded highway that was meant to ease travel to and from the capital will remain out of reach for the communities and businesses that depend on it.
The project's fate now rests with the responsible authorities and the contractor, who face mounting pressure to complete the remaining 54 percent of the work and deliver on a promise made more than a year ago.
For further details, read the original reports at Nepal Press and Khabarhub.