Tree felling for the construction of the 220 kV Dumre-Bharatpur transmission line, part of the Tanahun Hydropower Project, is progressing in forest areas along the route spanning Tanahun and Chitwan districts. According to project chief Shyamji Bhandari, approximately 50 percent of the trees that must be cut along the forest areas on the transmission route have been felled so far.

The tree-cutting work is being carried out at a rapid pace as the project moves to complete the transmission line, which is a key component in connecting the under-construction hydropower project to the national grid.

Transmission Line Work Gathers Pace

The Dumre-Bharatpur transmission line passes through forest sections in both Tanahun and Chitwan districts, requiring the felling of trees standing along the designated corridor. Project officials have confirmed that half of the required felling has already been completed.

Project chief Shyamji Bhandari said the work is being pushed forward quickly so that the transmission line can be finished on schedule. The urgency reflects the broader timeline of the Tanahun Hydropower Project, which depends on the line to evacuate the electricity generated once the project comes online.

The 220 kV Dumre-Bharatpur line is designed to link the project's power generation site near Dumre in Tanahun with Bharatpur in Chitwan, where the power will be connected to the national transmission network.

Forests Cleared Along the Route

The tree felling is concentrated in the forest areas that fall directly under the transmission route. Clearing the corridor is a prerequisite for erecting towers and stringing conductors across the two districts.

According to the project, about 50 percent of the trees that must be cut along the forest areas on the route have already been felled. The remaining trees are expected to be removed as the work continues.

Part of the Larger Tanahun Hydropower Project

The transmission line is being developed as an integral component of the Tanahun Hydropower Project, one of Nepal's significant hydropower undertakings. The project requires a dedicated transmission line to carry the electricity it generates to the grid, and the Dumre-Bharatpur 220 kV line has been planned for that purpose.

The rapid pace of tree felling underscores the pressure on the project to keep its construction schedule on track. Delays in completing the transmission line could affect the project's ability to deliver power once generation begins, making the clearing of the forest corridor a priority task for project officials.

As the work advances, the project is focused on completing the remaining felling along the route and moving ahead with the physical construction of the line through Tanahun and Chitwan.