The Infrastructure Development Office, Sindhulimadhi, under the Bagmati Province government, has issued a public notice warning that it will terminate the contract for the Sindhulimadhi-Bhumesthan-Chakamke-Udayapur-Katari road upgradation project over prolonged delays in construction work.
Through the notice, the office has directed the contractor, the Contech-Jayi-Jai Shambhu JV based in New Baneshwor, Kathmandu, to appear before it within 15 days with a satisfactory explanation regarding the delayed progress of the project. If the contractor fails to present a convincing justification within the given timeframe, the office has made clear that it will move to terminate the contract.
Contract signed in 2079 BS
The contract for the upgradation of the Sindhulimadhi-Bhumesthan-Chakamke-Udayapur-Katari road was signed on Jestha 17, 2079 BS, entrusting the work to the Kathmandu-based joint venture. Despite the considerable time that has elapsed since the agreement, the physical progress of the road project has reportedly failed to keep pace with expectations, prompting the Infrastructure Development Office to take a firmer stance.
The Sindhulimadhi-Katari road is a significant route within Bagmati Province, and its upgradation has been a priority project for the provincial government. Continued delays have raised concerns about the inconvenience faced by local residents who depend on the route for transportation and access to markets and services.
Office steps up pressure
By issuing a public notice, the Infrastructure Development Office, Sindhulimadhi has escalated its response to the stalled works. The 15-day ultimatum is intended to compel the contractor to either accelerate the pace of construction or provide legitimate reasons for the shortfall. Such notices are a standard administrative step taken by government offices before initiating contract termination proceedings against underperforming contractors.
The office's move signals growing impatience within the provincial infrastructure machinery over the slow execution of the project. The warning makes clear that the responsibility for the road's completion now rests squarely on the contractor, and that the office is prepared to enforce the terms of the agreement should the deadline pass without a satisfactory response.
What happens next
Attention now turns to whether the Contech-Jayi-Jai Shambhu JV will come forward within the 15-day window to explain the delays or commit to a revised schedule for completing the remaining works. The office's notice remains in effect, and the fate of the contract will depend on the contractor's response in the coming days.
If the contract is ultimately terminated, the Bagmati Province government would need to decide the next course of action for the road upgradation project, which remains an important infrastructure commitment for the communities along the Sindhulimadhi-Katari corridor. For now, the public notice stands as the office's strongest signal yet that it will no longer tolerate inaction on a project that has remained pending since the agreement was signed on Jestha 17, 2079 BS.