Nepali Army installs 27.43-metre Bailey bridge over Budhi Gandaki at Aarughat in two days

The Nepali Army completed the installation of a 27.43-metre Bailey bridge over the Budhi Gandaki River at Aarughat in two days, connecting Dhading and Gorkha districts, and handed it over to the Gorkha Road Project on Monday.

The Patrukar
The Patrukar
3 Kartik 2083 BS 4 mins read
Nepali Army installs 27.43-metre Bailey bridge over Budhi Gandaki at Aarughat in two days

The Nepali Army has completed the installation of a 27.43-metre-long Bailey bridge over the Budhi Gandaki River at Aarughat, finishing the work in just two days, according to the Army's Directorate of Public Relations and Information. The bridge, which connects Dhading and Gorkha districts, was formally handed over to the Gorkha Road Project on Monday, and the entire installation was carried out by the Nepali Army. The completion of the span, delivered across a river that runs between the two districts, was reported by Khabarhub and My Republica, both of which cited the Directorate's statement.

Installed in two days, handed over on Monday

According to the Directorate of Public Relations and Information, the 27.43-metre Bailey bridge was installed over the Budhi Gandaki at Aarughat in a compressed two-day operation. The Directorate confirmed that the work was carried out by the Nepali Army and that the completed structure was transferred to the Gorkha Road Project on Monday.

Key facts at a glance

  • Structure: a 27.43-metre-long Bailey bridge
  • Location: over the Budhi Gandaki River at Aarughat
  • Districts connected: Dhading and Gorkha
  • Installation time: two days
  • Executed by: the Nepali Army
  • Handed over on: Monday, to the Gorkha Road Project

Installing a steel truss span of nearly 28 metres is not a matter of dropping a ready-made bridge into place. Bailey bridges are assembled from prefabricated components on the riverbank, joined together into trusses, launched across the gap and then finished with a deck that vehicles can use. Completing that entire sequence in roughly 48 hours reflects the pace of a trained military engineering crew working with familiar equipment, and it is the two-day timeline that gives the Aarughat operation its distinction.

A bridge type built for speed

The Bailey bridge has long been the structure of choice wherever a crossing is needed quickly. It is a prefabricated steel truss bridge, designed so that its standard components can be transported by truck, moved to site and assembled with relatively light equipment, often without heavy cranes. That modularity is precisely why armed forces around the world, including the Nepali Army, maintain Bailey bridge sets: the same panels and parts can be configured into spans of different lengths to suit the gap at hand.

In Nepal, the value of that flexibility is easy to see. Rivers descend from the Himalaya through the mid-hills, cutting across the routes that roads must follow, and Aarughat sits along one of the significant waterways of the Gandaki river system. A span of just over 27 metres, such as the one now standing over the Budhi Gandaki, falls within the normal range of the bridge type, and the speed of assembly means a crossing can be established within days rather than over the far longer period that a permanent structure would demand. For an army engineering team, the Aarughat job was therefore a textbook task: a known bridge design, standard components and a defined gap, executed at pace.

Connecting Dhading and Gorkha across the river

The new bridge establishes a direct connection between Dhading and Gorkha districts at a point where the Budhi Gandaki forms a natural barrier between them. For residents, travelers and traders, that connection is the practical heart of the project: it links the two banks at Aarughat and allows people and goods to move between the districts across a river that would otherwise interrupt the route.

With the handover complete, the bridge has passed from the Army's installation crew to the Gorkha Road Project, the body that now takes the structure forward. The handover on Monday is the formal marker of that transition. The Army's task was to deliver the bridge; the road project's task is to carry it as part of its network going forward.

The Army's engineering role and what comes next

The Nepali Army's Directorate of Public Relations and Information made the completion public, and the operation itself was carried out by the Army from start to finish. The two-day installation at Aarughat illustrates why tasks of this kind fall to the military: bridging work demands trained personnel, standardised equipment and tight coordination on site, and the Army brought all three to the riverbank within the short window the job required.

For the Gorkha Road Project, the arrival of the bridge adds a 27.43-metre structure over the Budhi Gandaki to its responsibility. For the two districts it connects, the outcome is straightforward. After a two-day installation by the Nepali Army, there is now a Bailey bridge at Aarughat, formally handed over on Monday, linking Dhading and Gorkha across the Budhi Gandaki.

Sources

Clustered via K cha khabar.

Related Articles

Nepal Lose to Canada by 24 Runs in World Cup League 2
News

Nepal Lose to Canada by 24 Runs in World Cup League 2

Nepal were bowled out for 232 while chasing 257 against Canada at Al Amerat Cricket Ground in Oman. Arjun Kumal scored 87, and Nepal now need to beat Oman in their final match to secure a top-six finish.

The Patrukar 3 Kartik 2083 BS